Skip to main content

Boiler mountings( parts attached to the pressure parts of boiler)

1. saftey valve
2. main steam stop valve( SDNR)
3. feed check valves (SDNR)

4. Blow down valves( two sets- first must be open fully and second must br crack open)
5.Air vents
6.chemical dosing valves
7. salinometer vale( cooling must be done for the samples).
8 soot blower steam valves
9. pressure gauge
10. thermometer
11. gauge glass

Comments

Popular posts from this blog

Why atomisation test should not be done in slide type fuel valves

Since very small needle lift is obtained in the test equipment result in an unequal pressure distribution in the cut off shaft resulting in a hard contact in a small area along with high frequency oscillations, low lubricity of test oil will increase the chance of seizure. Full lift and high lubricity of heavy oil eliminates this risk  of seizure during normal operation.( Always open and clean slide type valves before testing as cold sticky heavy oil along with small clearances can cause restriction in the movement of the spindle).