Gauge glass blow through

1. clearing water side: close steam and water valve,  open drain cock, then open water cock and see water is coming. Close water cock.
2. clearing steam side, open steam cock, open drain(steam cock shud be kept open for only one to 2 secs.).

Putting back to operation- close all cocks, then open water cock fill water inside, then open steam cock.

Comments

Popular posts from this blog

Why atomisation test should not be done in slide type fuel valves

Since very small needle lift is obtained in the test equipment result in an unequal pressure distribution in the cut off shaft resulting in a hard contact in a small area along with high frequency oscillations, low lubricity of test oil will increase the chance of seizure. Full lift and high lubricity of heavy oil eliminates this risk  of seizure during normal operation.( Always open and clean slide type valves before testing as cold sticky heavy oil along with small clearances can cause restriction in the movement of the spindle).