How to check tie-rods are tightened to their correct pre-tension

Connect hyd-jacks to all the tie-rods together.operate the pump until prescribed hydraulic pressure and maintain the pressure. Check the clearance between the nut and intermediate ring (or contact
surface as in MAN B&W) with a feeler gauge, if clearance exist then the nut is tightened onto the intermediate ring and the pressure released. if a tie bolt is found broken, it must be immediately replaced, otherwise fretting and premature failure may occur.

Comments

Popular posts from this blog

Why atomisation test should not be done in slide type fuel valves

Since very small needle lift is obtained in the test equipment result in an unequal pressure distribution in the cut off shaft resulting in a hard contact in a small area along with high frequency oscillations, low lubricity of test oil will increase the chance of seizure. Full lift and high lubricity of heavy oil eliminates this risk  of seizure during normal operation.( Always open and clean slide type valves before testing as cold sticky heavy oil along with small clearances can cause restriction in the movement of the spindle).